Design Build Bid Preparation Question:
What if the Alternate Technical Concept discussion results in a new design exception?

Answer:
If an Alternate Technical Concept results in a design exception, the design exception will need to be approved and then an addendum will need to be published for the bid package to incorporate the design exception.