Question:
If an inspector is requested long after the start of the project, does that inspector have to equal or exceed the qualifications of the staff proposed in the SOI?
•
Answer:
If an inspector is requested within 2 weeks from the anticipated start dates identified in the RFP, then they must have to equal or exceed the qualifications of the staff proposed in the SOI.
Created by
Eric R Felty/PennDOT
on
04/01/2008
at
09:35:20 AM