Frequently Asked Question

Design Build Preliminary Engineering Question:
What amount of conceptual MPT will be provided in Bid Package?

Answer:
Conceptual MPT plans are required for design field view approval which completes the preliminary engineering phase. As part of the Bid Package, the traffic requirements will be provided in the specifications. Conceptual MPT plans may be included as part of the bid package.